Goal Setting

Project Planning for Personal Goals: A Worked Example

By iDel Published · Updated

A personal goal becomes a plan when it is split into deliverables (things that will exist when the work is done), milestones (dated checkpoints at which a deliverable is finished) and next actions (steps small enough to start in one sitting). Two corrections keep that plan honest. The first is to adjust every estimate using how long your own past projects took, because people reliably predict that they will finish sooner than they do. The second is a pre-mortem, a short exercise in which you assume the project has already failed and list the reasons. A complete worked example, with hours, dependencies and a schedule, is further down.

Quick answer

StepWhat you produceSource of the idea
1. Define the end stateOne sentence plus a “done when” testNASA: completion of an element is “both measurable and verifiable”
2. Break into deliverablesA short list of nouns (the things that will exist)Product-oriented work breakdown structure (NASA handbook)
3. Plan near work in detail, far work roughlyWork packages now, planning packages laterNASA handbook, work packages vs planning packages
4. Estimate with an outside viewYour estimate multiplied by your own past overrunReference class forecasting (Flyvbjerg 2006)
5. Run a pre-mortemA list of failure reasons, each with a preventionGary Klein, Harvard Business Review, September 2007
6. Review weeklyMilestone met or replannedWeekly review

How do you break a goal into deliverables, milestones and next actions?

Start from what the finished project contains, not from what you will do. NASA’s Work Breakdown Structure Handbook defines a WBS as “a product-oriented family tree” of the hardware, software, services and other deliverables needed to reach the end objective, and says its purpose is to subdivide the work into manageable segments for planning and control of cost, schedule and technical content. In the handbook’s hierarchy, Level 1 is the entire project and the lower levels are progressively finer subdivisions of the products. NASA’s Core Financial System can capture costs to a maximum of seven levels, but the handbook adds that each branch only needs to be subdivided as far as needed for adequate management, insight and control.

For a personal project, three levels are normally enough:

  1. Deliverables. Nouns such as “interview notes”, “layout file”, “proof copy”. A deliverable has an owner (you) and a test for “done”.
  2. Tasks. The work that produces one deliverable, each with an hour estimate.
  3. Next actions. The first physical step of a task, small enough to start without further thinking, for example “email Aunt Mei to book a 90-minute call”. These are the lines that belong in a ten-minute daily plan.

A milestone is the moment a deliverable passes its “done when” test, with a date attached. Milestones are what you check in a weekly review; tasks and next actions are what you do between reviews.

The handbook’s own summary of the structure applies directly: it is product-oriented, “not an organizational structure”. Name the branches after the things you will have, not after the kinds of effort (for example “research”, “admin”) because effort-based lists hide whether anything is finished. The NASA handbook also describes a WBS dictionary, a short written definition of each element, prepared “to eliminate duplication and overlap of work assignments”. For one person, that becomes a single line per deliverable stating what is in and what is out.

Plan the near term in detail and the far term roughly

NASA’s handbook distinguishes work packages from planning packages. A work package “provides further detail on work content that is considered near-term, while a PP defines far-term work at a summary level.” Applied to a personal project, write tasks and hours for the next four to six weeks, and leave later deliverables as one line each until you reach them. The estimates for distant work are the weakest ones you have, and detailing them early only produces precise numbers that will change.

Why do your own estimates run short? The planning fallacy

Roger Buehler, Dale Griffin and Michael Ross, in “Exploring the ‘planning fallacy’” (Journal of Personality and Social Psychology 67(3), 1994), use the term “planning fallacy”, which they credit to Kahneman and Tversky (1979), for “the tendency to hold a confident belief that one’s own project will proceed as planned, even while knowing that the vast majority of similar projects have run late”. In their first study, 37 psychology students in the final semester of an honours thesis course at the University of Waterloo were asked when they would submit their thesis. Fewer than a third of them (29.7 percent) finished within the time they had called their best estimate. The 33 who had submitted by the time the records stopped, two semesters after the survey, had predicted a mean of 33.9 days and actually took 55.5.

Two further results matter for how you plan:

  • Worst-case guesses were not pessimistic enough. Asked for the date if everything went as poorly as it possibly could, the students gave a mean of 48.6 days, still below the 55.5 actually taken (a gap the authors report as not statistically significant), and fewer than half (48.7 percent) finished by that date. The authors conclude that asking for a pessimistic prediction decreased the optimistic bias but did not make the forecasts more accurate. When “everything went as well as it possibly could”, the mean was 27.4 days and 10.8 percent made it.
  • People know their record and still forecast optimistically. In a separate classroom survey, students reported having finished about two thirds of their previous projects (mean 68 percent) later than they expected. The authors point to people’s ability to hold “two seemingly contradictory beliefs”: although aware that most of their previous predictions were overly optimistic, they believe that their current forecasts are realistic.

The paper opens with large public projects. Citing P. Hall’s Great Planning Disasters (1980), it reports that according to original estimates in 1957 the Sydney Opera House would be completed early in 1963 for $7 million, and that a scaled-down version finally opened in 1973 at a cost of $102 million.

What fixes it: the outside view

Bent Flyvbjerg’s 2006 paper in the Project Management Journal explains the mechanism and the remedy. As he summarises the research, Kahneman and Tversky (1979) argued that the tendency to underweight or ignore distributional information, meaning the outcomes of similar ventures, is perhaps the major source of error in forecasting, and Lovallo and Kahneman (2003) traced the planning fallacy to an “inside view” that focuses on the specific planned action rather than on the outcomes of similar actions already completed. Using that distributional information is called taking an “outside view”, which Flyvbjerg calls “the cure to the planning fallacy”. Reference class forecasting, the method he describes for taking the outside view systematically, has three steps:

  1. Identify a relevant reference class of past, similar projects, “broad enough to be statistically meaningful but narrow enough to be truly comparable”.
  2. Establish a probability distribution for that class from credible empirical data.
  3. Compare the specific project with that distribution to find its most likely outcome.

The first practical use the paper reports was in transport: in 2004 the UK Department for Transport and HM Treasury decided to use the method in appraising large transport projects, and the reference class for roads alone held 172 completed projects. A person has a much smaller class: their own earlier projects. The mechanism still carries over, and one of Buehler’s own experiments supports a personal version. In Study 4, 123 students predicted when they would finish a computer assignment that took about an hour. One group recalled how they had done on similar past assignments before predicting; a second, “recall-relevant” group also answered questions that tied that history to the new task, for example when they would finish if they completed it as far before the deadline as they usually completed assignments. In the recall-relevant group, 60.0 percent finished within their predicted time, against 38.1 percent of those who only recalled and 29.3 percent of the control group. The abstract says the optimistic bias was eliminated in that condition; the results add that its predictions were less biased but no more accurate than those in the other two conditions. Linking a forecast to what actually happened last time reduced the optimism; it did not make the forecast precise.

A workable personal routine follows from that:

  • Keep a log of three to five finished projects with the estimate you made and the hours or weeks they took.
  • Divide actual by estimated for each. Take the middle value as your multiplier.
  • Apply it to the total of your task estimates, and decide whether the padded total fits the time you have.

Where the padded total does not fit, the options are the same as in any project: more weekly hours, a later date, or less scope.

What is a pre-mortem and how do you run one?

Gary Klein’s “Performing a Project Premortem” appeared in the September 2007 issue of Harvard Business Review. In its summary, team members “assume that the project they are planning has just failed” and then generate plausible reasons for its demise. The article opens with the case for it: projects fail “at a spectacular rate”, and one reason is that too many people are reluctant to speak up about their reservations during planning. Klein’s own site describes the session: it typically begins after a team has been briefed on a plan, the leader asks everyone to imagine the plan has failed, and everyone contributes the potential threats and hurdles. In the HBR article, each person first spends a few minutes independently writing down every reason they can think of, the reasons are then read out one at a time until all are recorded, and afterwards the project manager reviews the list for ways to strengthen the plan.

Klein built the method on prospective hindsight, “imagining that an event has already occurred”, and cites 1989 research by Deborah J. Mitchell, Jay Russo and Nancy Pennington as finding that it “increases the ability to correctly identify reasons for future outcomes by 30%”. The study’s own abstract (Mitchell, Russo and Pennington, Journal of Behavioral Decision Making, 1989) puts the result in different terms: in the first of its two experiments, whether an event was set in the past or the future “showed little influence”, while certainty about the outcome strongly affected the explanations; those for events treated as certain “tended to be longer” and contained a higher proportion of episodic reasons. Either way, the exercise starts from a failure stated as certain: Klein’s session leader opens by announcing that the project “has failed spectacularly”.

A solo version takes about 20 minutes:

  1. Write the sentence “It is the deadline and the project failed.”
  2. List every reason you can think of, with no filtering, for five minutes.
  3. Mark the three most likely and the three most damaging.
  4. For each marked reason, add either a prevention step to the task list or an early warning sign to check at the weekly review.

On your own you have no colleague who is reluctant to speak, but you have the same blind spot: the plan you just wrote feels complete. Writing the failure first gives you permission to be critical of it.

Worked example: a 48-page family history booklet

The project below is illustrative. All hour figures are invented planning assumptions for the example, and the 1.5 multiplier stands for a hypothetical personal log (three past projects that ran 1.4, 1.6 and 1.5 times their estimates, median 1.5). It is not a research finding.

Goal. A printed family history booklet of 6 chapters and 40 or more photos, in hand within 17 weeks, working 6 hours a week.

Done when. The printed copies are in hand, made from a proof that was checked against the final file.

IDDeliverableTasksInside-view hours (illustrative)Depends onExternal waitDone when
D1Interview notesBook 4 interviews (1 h), hold them (4 x 1.5 h), write them up (4 x 1.75 h)14NoneRelatives’ availability4 typed notes files saved
D2Photo archiveScan about 60 items (5 h), caption and file them (3 h)8NoneNone40 or more captioned images in one folder
D3Draft text6 chapters x 2.5 h15D1None6 chapters, one file
D4LayoutPage template and placement (8 h)8D2, D3None48-page PDF
D5Reviewed textRead-through requests (2 h), apply corrections (5 h)7D42 weeks for 2 readersCorrections applied
D6Printed proof and orderCheck printer file rules and proof (4 h)4D51 week printingProof matches final PDF
Total563 weeks

Two plans can now be compared.

Inside view. 56 hours at 6 hours a week is 9.3 weeks, plus 3 weeks of waiting: about 12 to 13 weeks. This is the plan that feels reasonable.

Outside view. 56 x 1.5 = 84 hours; 84 divided by 6 is 14 weeks, plus 3 weeks of waiting: 17 weeks.

MilestonePadded hours (illustrative, x 1.5)Cumulative padded hoursCalendar week finished (6 h/week, waits included)
D1 Interview notes2121Week 4
D2 Photo archive1233Week 6
D3 Draft text22.555.5Week 10
D4 Layout1267.5Week 12
D5 Reviewed text10.578Week 15 (includes 2 weeks waiting for the readers)
D6 Printed proof and order684Week 16; printed copies delivered in week 17 after 1 week of printing

Because D1 and D2 do not depend on each other, the first 6 weeks can interleave them, so a delayed interview does not stop the scanning. D3 cannot start until D1 is complete, which makes the interviews the critical dependency and the reason they are booked in week 1. The chapter count of 6 was chosen after the first pass: an 8-chapter version added 5 more draft hours, 61 in total, which at 1.5 would have come to 91.5 hours.

Next actions for week 1

  • Email two relatives to propose interview times.
  • Open a folder named “family-book” and a one-line note listing the “done when” test.
  • Photograph the 10 most important prints to confirm the scanning rate (the 5-hour estimate rests on about 5 minutes per item).

Pre-mortem on the same project

Imagined cause of failurePrevention or early warning
A key relative is not available until lateOffer a phone call as a fallback; if no interview is held by the end of week 2, move the missing chapter to the “later” list
Photos arrive with no names or datesCaption each item during scanning, not afterwards
New stories keep adding chaptersA “later” list; the chapter count stays at 6 unless a swap is made
The printer rejects the fileRead the printer’s file requirements before starting layout (D4)
Weekly hours slip to 3The review checks hours logged against 6; two short weeks in a row trigger a replan of the date

When a project stalls

When progress stops, find the cause before adding tasks.

  • The next action is unclear. Break it down until the first step is something you can finish in 30 minutes. If a step keeps getting postponed, an if-then plan ties it to a time and place.
  • One big task is blocking everything. Cut it into pieces and start with the smallest.
  • The time went elsewhere. Decide whether the project still matters, then reserve sessions or move the date. A moved date is a replan, not a failure, and the weekly review is where it happens.
  • Scope grew. New ideas go on the “later” list. If something must come in, something of similar size must go out.

For goals that come from a larger yearly plan, the quarterly planning system shows where a project like this fits among others competing for the same hours.

Tools

A notebook page, a spreadsheet with the columns shown in the table above, or a nested list in any notes app is enough for a project of this size. The overhead of the tool should stay small against the work itself; if setting up the tracker takes two hours for a 56-hour project, the setup is too elaborate.

Sources